Ongoing
Construction Report

Barn Project,
Kandern, Germany


30 Sept. 2007



Barn as of Sept. 9, 2007

Barn as of Sept. 23, 2007
 

The structural phase of the Barn Project continues. We are pouring foundations and floors, building load-bearing walls and removing the last of the inner walls and flooring. The following photos are from 30 September.


Barn as of Sept. 30, 2007

You can see the first floor getting ready for pouring on the right by the tool room entry.


(L to R) Entry & Elevator Shaft / Ground Floor Apt. & Tool Room Entry / Crane in Courtyard


Two Views of the 1st Floor

Electrical wiring had to go in before pouring the 1st floor. Pouring should happen this week.


Cellar Tool/Storage Room --- Ground Floor Entry by Elevator Shaft

We are continuing to work on the ground floor, building non-load bearing walls and getting things
ready for finishing work. After the first floor is poured we will work on load bearing walls for the 2nd floor.